What Is a Cost Overrun? Causes and Prevention
A cost overrun is the amount by which a job's actual or projected cost exceeds its approved budget for the same scope of work. It differs from a change order, which changes the budget and usually the price when the scope changes, and on a fixed-price job an overrun comes straight out of profit.
If slow labor and higher fixture prices push the cost of a plumbing contractor's $186,000 job, budgeted at $150,000, to $160,660 with no change in scope, that's a $10,660 overrun and profit drops from $36,000 to $25,340.
What a cost overrun means in practice
Who pays for an overrun depends on the contract. On a fixed-price or lump-sum contract (one set price for the whole job), the contractor absorbs it unless the contract gives a way to recover the money. On a cost-plus job (your costs plus a fee) or a time-and-materials job (hours and materials at agreed rates), the owner often pays, sometimes up to an agreed cap.
Owners use the word differently: their overrun is a project that cost more than their budget, and it can include approved changes. A Purdue study of Indiana Department of Transportation contracts from 1996 to 2001 measured it that way, comparing final cost, including change orders and claims, with the award amount. About 55% of contracts ran over, by 4.5% overall, from 2.6% on road resurfacing to 8.1% on bridges. This post uses the contractor's meaning, a job that cost more than its estimate for the work it was paid to do.
Common causes of cost overruns
Most overruns start in one of these places:
- A short estimate, such as a material count (takeoff) that missed a floor or labor hours copied from an easier job.
- Unpriced extra work, where the crew did what was asked and nobody wrote it up.
- Price moves after the bid, because the quote on the copper or lumber had expired.
- Lost labor productivity from rework, waiting on another trade or poor site access.
- Schedule slips, which keep rentals, supervision and temporary power running longer.
- Conditions nobody could see at bid time, like rock in a trench, where the contract may or may not let you recover the cost.
Cost overrun vs change order
Ask one question: did the scope of the work change? If it did, and the change is approved in writing, it's a change order. If the work stayed the same and the cost went up, it's an overrun.
| Cost overrun | Change order | |
|---|---|---|
| What happened | Same work cost more than planned | The work itself changed |
| Budget | Stays the same | Goes up or down |
| Contract price | Stays the same on a fixed-price job | Usually adjusted |
| Who absorbs it | Depends on the contract, often the contractor | The customer, if priced and signed |
The danger zone is between the two. Extra work done on a verbal okay can start as a change and end as an overrun if nobody will sign for it later. Our guide to construction change orders covers the request, price and approve process that keeps that from happening.
On federal fixed-price construction contracts with the FAR 52.243-4 Changes clause (June 2007 version), an oral order counts as a change only if it comes from the contracting officer, the government official who can change the contract, and the contractor gives written notice that it treats the order as a change. Costs incurred more than 20 days before that notice aren't adjusted, except for defective specifications.
The contractor then has 30 days to assert its right to an adjustment, unless the government extends that, and nothing is allowed after final payment. A subcontractor looks to its own subcontract, not this clause. Private contracts set their own rules, so read yours before the work starts.
Tracking estimate vs committed vs actual
Three numbers tell you where a job really stands, because each one catches a dollar at a different stage.
The estimate, or budget, is what you planned to spend. Actual cost is what has already hit the books: posted payroll, entered bills, coded card charges. Between them sit committed costs, money you've agreed to spend through purchase orders and subcontracts but haven't been billed for yet.
Then add the work nobody has bought yet. Committed costs plus that remaining work make up your cost to complete, your current estimate of what's left to spend. The projected final cost is actual plus cost to complete. Compare that total with the budget, by cost code (the label for each type of work, such as labor or fixtures). Our post on construction cost codes explains how to set those up.
Actual cost on its own lags by weeks. A $31,500 fixture order is a real obligation the day you sign it, even if the bill won't arrive for two months.
Early warning signs of an overrun
These usually show up well before the budget runs out:
- Labor hours per unit, or per room or foot of pipe, running above the estimate.
- Actual plus committed on a cost code passing its budget with work still to do.
- Percent of budget spent running ahead of percent of work complete.
- Extra work in daily logs with no matching change request.
- A forecast nobody has changed in a month, on a job that's clearly moving.
Worked example: catching an overrun at week six
A plumbing contractor has a $186,000 fixed-price contract to rough in 24 apartments (install the pipes before the walls close) and supply the fixtures, which the general contractor's crew will set. The $150,000 budget includes 1,300 labor hours at $60 an hour, including payroll taxes and benefits, and a $6,000 contingency, money set aside for surprises. At week six, 10 of the 24 units are roughed in, or 41.7% of the job. Spending is $66,100, or 44.1% of budget. That's only a 2.4-point gap, the kind most people wave through.
The crew has used 640 hours on 10 units, or 64 per unit against the 54.2 budgeted. At that pace the other 14 units need 896 hours, or $53,760. The signed fixture order also came in $2,500 over the materials line.
| Cost code | Budget | Actual | Committed | Still to come | Projected final | Over (under) |
|---|---|---|---|---|---|---|
| Labor | $78,000 | $38,400 | $0 | $53,760 | $92,160 | $14,160 |
| Materials and fixtures | $48,000 | $19,000 | $31,500 | $0 | $50,500 | $2,500 |
| Subcontractors | $12,000 | $4,800 | $7,200 | $0 | $12,000 | $0 |
| Permits and equipment | $6,000 | $3,900 | $0 | $2,100 | $6,000 | $0 |
| Contingency | $6,000 | $0 | $0 | $0 | $0 | ($6,000) |
| Total | $150,000 | $66,100 | $38,700 | $55,860 | $160,660 | $10,660 |
Even after using the whole contingency, the job is heading $10,660 over. Profit falls from $36,000 (19.4% of the price) to $25,340 (13.6%).
The hours are the fixable part. The foreman says crews keep working around framing that isn't ready. The contractor resequences the remaining units and puts the crew on the ones that are ready, and the next two come in at 58 hours. If that holds across the 14 remaining units, that's 812 hours, or $48,720, which saves $5,040. The projected final cost drops to $155,620, still $5,620 over budget, but profit recovers to $30,380 (16.3%).
During those weeks, the owner asks to move laundry hookups in six units. It adds $4,000 of cost. The contractor prices it at $5,200 and gets it signed, so the budget becomes $154,000 and the contract $191,200. Had the crew just done it, that $4,000 would have been more overrun.
How to respond and how to prevent the next one
When the forecast goes over, work through it in order:
- Rule out coding errors, since a charge on the wrong job makes two false variances.
- Find the cause and decide whether it's price, quantity or schedule.
- Update the forecast for every cost code the cause touches.
- Choose a response, such as resequencing, renegotiating a quote, submitting a change request or billing a subcontractor for rework they caused.
- Tell whoever answers for the job's profit now, not at the end of the job.
Get quotes that stay valid through your buying date, buy major materials early, and carry a contingency based on your own past jobs. Compare actual to estimate after every job and feed the differences into the next bid, since a labor miss that repeats is an estimating problem. Job costing for contractors covers the cost codes and weekly reconciliation that make that comparison possible.
Seeing overruns while there's time to act
The actual column is only useful if it's current, and card charges and bills often reach the books long after the crew has moved on. With job costing in Clyr, expenses land on the job and cost code while the crew is still on site, and budget versus actual reflects them. The insights engine also watches for budget trends and sends findings in a weekly digest. Your project manager still supplies the forecast.
FAQs
No. Scope creep is one cause. It means the work grows bit by bit without anyone formally agreeing to it, like one extra outlet here and a moved door there. Each small addition costs real money, and with no change order behind it, that money shows up as overrun. An overrun can also happen with no scope creep at all, for example when a supplier's price jumps.
Yes, on any work with a budget and a defined scope. A roofer on a fixed-price reroof for a property manager can overrun when the tear-off takes twice as long as planned, and an IT consultant can overrun on a fixed-fee software setup. The tracking is the same, whatever the trade.
Measure it against profit, not just cost. The $10,660 in the plumbing job is 7.1% of the budget, which might sound tolerable. It's also 29.6% of the planned profit. Set your trigger in those terms, such as any forecast that takes more than 10% of a job's planned profit, and review the job that week.
It can. Under the percentage of completion method, revenue depends on costs to date divided by estimated total costs. A higher estimate lowers the percent complete, so revenue recorded so far falls, and you may reverse some profit already booked. That's why an updated forecast can hurt a quarter's results before the extra money has been spent.