What Is a Back Charge in Construction?
A back charge is a cost a general contractor bills to a subcontractor, usually by deducting it from the next payment, to recover money it spent fixing a problem the subcontractor caused, such as debris left behind or defective work that had to be redone. The subcontract decides when one is allowed.
If a painter's lift gouges a finished storefront door and the general contractor (GC) pays $650 to replace it, the GC can take that $650 out of the painter's next check, as long as the subcontract allows it and the GC followed its notice steps.
Why back charges exist
The GC answers to the owner for the whole project. When a subcontractor (sub), a trade company hired for one part of the job, leaves a mess or falls behind, the GC often can't wait. It fixes the problem itself, then charges the cost to the sub responsible.
The right usually comes from the subcontract. Contracts call it a back charge, backcharge, set-off or contra charge, and they set the terms: what can be charged, the notice, the time to fix the problem, any markup and how the money is collected. If your subcontract is silent, a back charge is much harder to defend.
Common causes of back charges
The usual causes are:
- Cleanup the sub was supposed to do and didn't, usually billed as labor hours plus dumpster fees.
- Damage the sub's crew did to the building or another trade's finished work, like a cracked window or a gouged floor.
- Rework, when defective work has to be redone by someone else because the sub didn't fix it.
- Delays that cost the GC or other trades money, such as extra weeks of equipment rental or overtime.
Delay charges are the most fought over, because proving one trade caused a slip is hard when several were working at once. Splitting one cleanup bill evenly across every sub on site invites disputes too. Tie each charge to the sub whose debris it was.
Notice and documentation a GC needs
These steps follow how many subcontracts handle it, but your contract's wording controls:
- Read the clause for the notice it requires, the days the sub gets to fix the problem (the cure period), any markup and how the charge is collected.
- Send written notice when you find the problem, saying what's wrong, where, which part of the contract it breaks and the deadline to fix it. Attach dated photos.
- Give the sub its chance to fix it. If the sub does, there's no back charge.
- If not, do the work and track the cost on its own, with a separate cost code (the label that sorts job costs by type of work) or work order, signed daily time tickets and invoices.
- Send a back charge notice with the total and the backup before you deduct anything, and deduct only as the contract allows.
Federal jobs add a rule for money held back until a sub fixes a problem. FAR 52.232-27, Prompt Payment for Construction Contracts (Jan 2017), goes in federal construction contracts. A prime contractor (the one holding the government contract) that has billed the government and, before paying a sub, finds part of that payment subject to withholding under the subcontract must notify the sub in writing. A copy goes to the contracting officer, the official running the contract. The notice states the amount, the specific causes and what the sub must do to get paid.
That notice must go out before the sub's payment is due, generally 7 days after the government pays the prime, and it's what lets the prime withhold without owing the sub late-payment interest. Once the sub corrects the problem, the prime has 7 days to pay, or 7 days from recovering the money if it reduced its next bill to the government, or it owes interest. It also owes the government interest on money it received and held back.
A charge for work you already did isn't the same thing, so on a federal job, have a construction attorney check how it fits.
State law can limit how much a GC holds. In Florida, on written contracts to improve real property where the state's construction lien law applies, section 715.12 of the 2026 Florida Statutes stops a GC using one disputed charge to hold back pay for work the dispute doesn't touch, unless the contract specifically says otherwise. Other states set their own rules, so a construction attorney can confirm yours.
Worked example: pricing a back charge
A GC is renovating a three-story office. The drywall subcontract requires daily scrap removal and allows back charges at cost plus 10% after 48 hours' written notice. On May 12 the superintendent finds scrap across floors 2 and 3 and emails the sub a notice with photos and a May 14 deadline, which this subcontract accepts as written notice. Nobody shows up, so on May 15 the GC's laborers clear both floors and the hauler swaps a full dumpster.
| Item | How it's calculated | Amount |
|---|---|---|
| Laborers | 15 hours x $48 burdened rate | $720 |
| Dumpster swap | Hauler's invoice | $480 |
| Subtotal | $720 + $480 | $1,200 |
| Markup allowed by the subcontract | 10% x $1,200 | $120 |
| Back charge | $1,200 + $120 | $1,320 |
The burdened rate is the hourly wage plus payroll taxes, insurance and benefits. The drywall sub's May pay application, its monthly bill, is $24,000. With 10% retainage, money kept back until the job is finished, $21,600 is due. After the back charge, the GC pays $20,280 ($21,600 - $1,320).
How a back charge is recorded on both sides
In double-entry bookkeeping, the debits and credits in every entry must match:
| Entry | Account | Debit | Credit |
|---|---|---|---|
| GC: cleanup done | Job cost: site cleanup | $1,200 | |
| Payroll and burden accrued (wages, taxes, insurance, benefits) | $720 | ||
| Accounts payable: waste hauler | $480 | ||
| GC: back charge issued | Accounts payable: drywall sub | $1,320 | |
| Job cost: site cleanup | $1,200 | ||
| Other income: back charge markup | $120 | ||
| Sub: back charge accepted | Job cost: back charges | $1,320 | |
| Accounts receivable: GC | $1,320 |
The payable and accrued lines are what you owe. Other income is money that isn't part of normal job revenue.
On the GC's books, the second entry takes the cleanup cost code back to zero and cuts what it owes the sub, its accounts payable, from $21,600 to $20,280. The $2,400 of retainage sits in its own retainage payable account (retainage receivable on the sub's books) and isn't touched. Some contractors credit the $120 markup to job cost instead; pick one treatment with your CPA.
On the sub's books, accounts receivable (money owed to the sub) was $21,600 after billing. Accepting the back charge moves $1,320 into job cost, so the job report shows what the cleanup really cost, and the $20,280 payment clears the rest. Some subs record it as a reduction of contract revenue instead.
How a subcontractor can dispute a back charge
Answer in writing, within the deadline your subcontract sets, and say exactly what you dispute and why. Then ask for the backup: the notice, photos, time tickets and invoices.
The usual grounds for a dispute are:
- No notice, or no real chance to fix the problem before the GC did the work.
- The debris or damage belonged to another trade.
- The hours, rates or markup go beyond what the contract allows.
- The work was extra scope, say patching the plumber's holes, which calls for a change order, not a back charge.
Offer a fix where you can, such as sending a crew or proposing a lower number. On the books, a disputed back charge stays in accounts receivable, tagged as disputed. If at month-end you expect to lose part of it, your bookkeeper can record that part as a cost against an allowance, a reserve that reduces the receivable.
Say the two sides settle at $800 after the drywall sub shows that part of the scrap was the framer's. That leaves $520 to give back ($1,320 - $800). The GC debits the cleanup cost code (and other income, if the markup goes too), credits accounts payable and pays it. The sub books $800 as job cost, less anything already recorded against an allowance, and collects the $520.
List a still-disputed back charge as an exception on your final lien waiver if the form has room for it. Lien waiver forms vary by state and some have no such line, so ask a construction attorney before you sign. And before your next subcontract, ask for wording that requires written notice of the default and reasonable time to correct it before any cost is charged to you.
Tracking back charges day to day
When a sub disputes a back charge, the records decide it. Code every cost behind it to the job and a dedicated construction cost code.
Some of that cost lands on company cards, such as cleaning supplies or a replacement door. Clyr's expense management for construction connects to the cards you already have, including Amex, Visa and Mastercard. The moment a card is swiped, Clyr texts the employee, who replies with a photo of the receipt, and the expense carries the job, the cost code and the GL account (the category in your books).
FAQs
No. A chargeback is a card payment reversed through the card network after a cardholder disputes it with their bank. A back charge is a deduction between two construction companies under their contract, and no bank is involved.
Then the GC invoices the sub and records a receivable, money the sub now owes it, instead of reducing a payable. If the GC still holds the sub's retainage, the subcontract may allow the charge to come out of it. Otherwise it's collected like any other unpaid bill.
Yes, if the prime contract between the owner and the GC allows it. When a sub actually caused the problem, the GC passes the charge down, which only works if the subcontract carries matching terms.
Some subcontracts set one. Even without a deadline, a back charge sent months later, often in a batch at the end of the job, is the hardest kind to defend: the photos are lost and the crew has moved on. Issue it in the same pay period as the problem.