What Is Maverick Spend and How Do You Stop It?
Maverick spend is company money spent outside the agreed way of buying: purchases from vendors you haven't approved, off-contract buys when a negotiated deal exists, or purchases that skip your policy. It's also called rogue spend or off-contract buying, and it often comes from convenience or habit rather than dishonesty.
When an HVAC company pays $38 for a capacitor at its supply house but a tech pays $61 for it at a retail store, the company pays $23 more to a store that isn't on its vendor list and has no agreed price.
What counts as maverick spend
One academic definition is narrow. A study of Finnish government buying by Katri Karjalainen and Erik van Raaij defines maverick buying as off-contract buying of goods and services where an established process already exists, built on pre-negotiated contracts with selected suppliers. In a 30-person contractor, that "contract" may be nothing more than account pricing at two supply houses and a list of approved subs.
Most businesses use the term more loosely, to include anything bought outside the policy. Common examples:
- A crew buys fittings at a hardware chain when the job's supply house has them at account price
- A property manager calls a handyman from a flyer when the approved maintenance vendor was available
- An office manager puts a software subscription on a personal card and asks to be reimbursed
- A project manager splits a $6,000 order into three invoices to stay under a $2,500 approval limit
It isn't the same as tail spend, the many small purchases from vendors you rarely use. Tail spend is about size, and maverick spend is about the route the purchase took. A $40,000 equipment order that skipped approval is maverick spend, and nobody would call it tail spend.
What it really costs
Price is only the first cost. Karjalainen and van Raaij point out that people who find a cheaper local option tend to ignore their own search time, the discounts lost when contracted volumes aren't reached, and guarantee and after-sales terms.
Back to the capacitor. Say that part should have been on the truck, and the tech drove 40 minutes round trip. His time costs you $55 an hour with wages and payroll costs, so the trip cost $36.67 ($55 x 40 / 60). Add the $23 price difference and that one part ran about $60 over what it should have cost.
Spend you can't see can't be used when you negotiate with the supply house. A handyman nobody set up as a vendor may have no insurance certificate on file. And a purchase with no job attached makes the job look more profitable than it was, until the charge turns up later.
Why people go off contract
The Finnish study, a survey run between November 2008 and March 2009, tested three reasons drawn from earlier research. Each has a direct match in the field:
- Expecting better terms, like the tech who's sure the store down the road beats the account price
- Wanting to keep an existing supplier, like the crew lead who has bought from the same counter for 15 years
- Not knowing a deal exists, like the new hire nobody told about the account
Field work adds a few more that the survey didn't test. The supply house is 40 minutes away or closed at 6 a.m. Approval takes longer than the drive to the store. The card works anywhere, so nothing stops the purchase. When you see a lot of maverick spend, look at the buying route first: distance, hours and approval time.
How to measure maverick spend
The basic formula:
Maverick spend rate = off-contract or off-policy spend / total spend in the categories where you have a deal or a policy
Export 12 months of card transactions and paid bills by vendor, keep only the categories you've actually set a rule for, and mark each vendor as agreed or not. Then sort the off-list spend into avoidable and justified, such as real emergencies. Here's a 45-person plumbing contractor looking at a year of parts and materials:
| Vendor group | Annual spend |
|---|---|
| Two supply houses with account pricing | $612,000 |
| Retail hardware chains | $94,000 |
| Other local suppliers | $33,000 |
| Online orders | $21,000 |
| Total | $760,000 |
Off-list spend is $148,000 ($94,000 + $33,000 + $21,000), so the rate is 19.5% ($148,000 / $760,000). Dispatch notes show $31,000 of that was after-hours or job-stopping emergencies, which leaves $117,000 that was avoidable, or 15.4% of the total.
To put a dollar figure on it, compare prices on the most common parts. If a sample shows off-list purchases running 18% above account price, that $117,000 would have cost about $99,150 on account ($117,000 / 1.18), so the overpayment is about $17,850. Those numbers are an example, not a benchmark. Your own rate, tracked month by month, is the one that matters. A property manager can run the same check per building, using the approved vendor list and paid work orders.
Controls that work in a 20-80 person company
The Finnish study's strongest finding was that people with less freedom in how they ordered, meaning documented procedures and clear responsibilities, reported less of all three kinds of maverick buying. People who felt undertrained reported more of two of the three. Those with less contact with the central purchasing team, and less say in its contracts, were more likely to go elsewhere for better terms. These are government buyers answering a survey, so read it as a pattern to test in your own company.
Here's how that looks with trucks and job sites:
- Put the approved vendor list, account numbers and agreed prices on every buyer's phone, and update it when something changes.
- Stock each truck with the parts your techs buy most, so the store run stops being the default.
- Ask crew leads which supply houses work before you sign a deal. They'll use a vendor they helped pick.
- Name one person who answers purchase questions by text within 15 minutes. If approval takes longer than the drive to the store, people will drive to the store.
- Require a purchase order, a written order listing the items and prices, above a set dollar amount, and approve bills with tiers like those in our invoice approval workflow guide.
- Tell accounts payable, the team paying vendor bills, not to pay a new vendor until someone has approved it.
Write down an emergency rule too. Decide what counts, who can buy, how much, and how soon the paperwork follows. Tulane University's purchasing manual offers wording worth borrowing, though it's only that university's rule: failing to anticipate an operating need isn't by itself an emergency, and an emergency order needs confirming paperwork within three days. Put your version in your business expense policy.
Then check. Each month, when you reconcile card statements, matching each charge to its receipt, have the service manager or owner read the off-list vendors by buyer. Under about 30 people, that's a 20-minute job for the owner. Past 50, give it to an operations manager and split it by branch or crew.
Go easy on penalties as your main tool. In the Finnish data, rewards and sanctions showed no link to any of the three reasons. The authors say a private company with bonuses could get a different result.
Common mistakes
Writing a rule nobody can follow is the big one. If the policy says every purchase needs a PO and the tech is standing at a counter at 6:30 a.m., you'll get workarounds and no data.
If crews keep finding a better price somewhere, that's information, not a violation, so go renegotiate or add the vendor. And keep the list current, because people stop trusting one with a closed branch on it.
How to see it day to day
You can only review what shows up with a name, a job and a receipt attached. Clyr's card expense management works on the cards you already have: when a card is swiped, it texts the employee, who replies with a photo of the receipt. Its insights engine checks spending daily and sends a weekly digest that flags split transactions and vendor concentration (a lot of spend going to one vendor), among other signals.
Card approvals in Clyr happen after the purchase, so it shows you what happened instead of stopping it at the counter, and your own rules still have to do that part.
FAQs
No. Often it's someone solving a problem the wrong way, and the purchase is real and for the business. The link is that the same gaps let fraud through. If nobody reviews off-list vendors, a fake vendor or a personal purchase can sit among them unnoticed. So your monthly review does double duty, even though you shouldn't treat every off-list buy as suspicious.
We don't quote one, because we couldn't trace the commonly repeated percentages to a primary source that fits a 20-80 person contractor or property manager. Your useful comparison is your own business over time. Measure a baseline for one category, make one change, and see whether the avoidable share falls over the next three or six months.
In the strict sense, no. If there's no agreed vendor or written rule, nobody can buy around it. You'd just have unmanaged spending. That's a good place to start: pull your top five spending categories, pick one or two preferred vendors for each and ask for account pricing, then write down what the rule is.
Ask why before you do anything else. The answer may point to a real gap, like a part the supply house never stocks or a route with no vendor nearby. Fix that, then restate the rule. If nothing changes and the reasons don't hold up, treat it as a management issue and consider reducing that person's spending authority.
Job costing means tracking each cost against the job that caused it, and off-list buying can throw it off. A purchase from an unfamiliar store is more likely to come in without a job code, so it lands in overhead (general business costs) or a suspense account (a temporary holding spot in the books) until someone sorts it out. Ask for the job name with every off-list purchase, even when the purchase itself is fine.