What Is Progress Billing?

Progress billing is a way of invoicing a long project in installments as the work gets done, instead of sending one bill at the end. Each invoice covers either a milestone the customer agreed to or the share of the work completed since the last bill, so cash comes in while the job is still running.

A mechanical contractor replacing a $148,000 heating and cooling system over three months might bill when the equipment arrives, when the ductwork is finished and when the system is running, instead of waiting for one check after the final inspection.

  • George Mahoney
  • 9 min read

Why businesses bill in stages

On any job that runs longer than a pay cycle, the costs come first. Crews get paid every week, the supply house wants its money in 30 days, and equipment rental runs by the month. Bill once at the end and you're financing the customer's project from your own bank account.

Progress billing moves money in step with the work, and the customer pays for work it can see.

Milestone billing vs percentage-of-completion billing

There are two common ways to decide what each progress bill covers.

Milestone billing ties a fixed amount to each agreed event: design approved, equipment delivered, system live. You bill when the event happens, whether that's two weeks or two months after the last invoice. A consultant setting up a new accounting system for $36,000 might bill $12,000 when the account setup is signed off, $15,000 when the system goes live and $9,000 after 30 days of support.

Percentage-of-completion billing, often called percentage-complete billing, runs on a calendar. Each month you bill the share of the work done since the last invoice. On construction jobs, that share is measured line by line against a schedule of values, the contract price split into pieces of work, and each line's percent complete times its value is what you can bill to date.

The Federal Acquisition Regulation (FAR), the rulebook for government purchasing, blurs the two. FAR 32.102, in the edition effective March 13, 2026, describes progress payments "based on a percentage or stage of completion," in line with the work accomplished, and on federal construction the prompt payment clause covered below counts "payments for reaching milestones" as progress payments.

Milestone billingPercentage-complete billing
When you billWhen each agreed event happensOn a set date, usually monthly
How the amount is setFixed amount or share of the price per milestonePercent complete times contract value, minus earlier bills
What proves itThe event itself, such as a sign-off, delivery or passed inspectionA progress estimate the customer, owner or architect checks
What gets argued aboutWhether the milestone is really doneThe percentage claimed on each line

How progress billing works, step by step

  1. Write the method into the contract, with the milestones or line items, the billing date, any amount held back and the backup each bill needs.
  2. At each milestone or cutoff date, measure progress by walking the job, counting what's installed or confirming the milestone is met.
  3. Prepare the invoice, showing the contract value, work completed to date, amounts billed before, anything held back, the amount due now and the balance left.
  4. Send it with the backup the contract calls for, such as photos, delivery tickets or lien waivers (signed releases of the right to file a claim against the property), and get it approved.

On commercial construction, steps 3 and 4 are usually a pay application, a formal payment request the architect checks, often on the G702 and G703 forms used in AIA billing. If the contract holds retainage, part of each bill is withheld until the work is substantially complete. For simpler jobs, Intuit's August 2026 help page describes a QuickBooks Online setting you turn on that splits an accepted estimate into several invoices and stops you billing past what's left of it.

One HVAC job billed two ways

A 15-person mechanical contractor signs a $148,000 contract to replace the heating, ventilation and air conditioning (HVAC) system in a two-story office building. The job takes three months. Assume no retainage.

Under milestone billing, the contract sets four payments that add up to $148,000: 35% when the equipment is delivered ($51,800), 30% when the ductwork and piping are in ($44,400), 25% at startup ($37,000) and 10% at final acceptance ($14,800). Under percentage-complete billing, the contractor bills monthly for the share of the job finished: 30% after month one, 75% after month two and 100% after month three.

End of monthWork completeBilled to date, milestonesBilled to date, percentage complete
130%, equipment on the roof$51,800$44,400
275%, ductwork and piping in$96,200$111,000
3100%, running and accepted$148,000$148,000

The percentage-complete invoices are $44,400 in month one (30% of $148,000), $66,600 in month two (75% of $148,000 is $111,000, minus the $44,400 already billed) and $37,000 in month three ($148,000 minus $111,000). They add up to $148,000.

Milestone billing had billed more by the end of month one, because the delivery milestone was priced at 35% while only 30% of the work was done. In month two it fell behind: 75% of the job was finished, but only 65% had been billed ($96,200 of $148,000), because startup hadn't happened yet. If a milestone slips, all the work toward it waits to be billed. Under percentage-complete billing, partial progress gets paid every month.

Progress billing vs similar terms

Time-and-materials billing charges for hours and materials as they're used, with no fixed price to divide. Progress billing splits a fixed or capped price into installments.

A construction draw is a different flow of money: a lender releasing loan funds to the borrower as the project moves along. It's the owner's financing, not the contractor's invoice.

Billing isn't revenue, either: contractors that record revenue as the work progresses measure what they've earned with the percentage of completion method, and the gap between what's billed and what's earned shows up as over- or underbilling on a work-in-progress (WIP) report.

When a progress bill must be paid

How fast an approved progress bill gets paid depends on the contract and often on a prompt payment law. The federal government has one for its own contracts, and states write their own, which vary.

On federal construction contracts, the FAR 52.232-27 clause (January 2017 version, current in the March 2026 edition of the FAR) makes a progress payment due 14 calendar days after the billing office receives a proper payment request. Late payments earn interest automatically, as long as the invoice was proper, the government had approved payment and nobody disputed quantity, quality, compliance or the amount. No interest runs on amounts properly retained under the contract.

The same clause makes the prime contractor, the one holding the government contract, promise each subcontractor payment for satisfactory work within 7 days of receiving its own payment, with interest if it's late. The subcontract can still let the prime hold retainage, or withhold part or all of a payment under the subcontract's terms after written notice to the sub and the contracting officer.

State rules can look nothing like that. Florida's Construction Contract Prompt Payment Law (section 715.12 of the 2026 Florida Statutes) covers written contracts to improve real property, signed after 1992, where a construction lien is available. Florida public work has its own sections, such as s. 218.735 for local governments.

The private-work law sets no single deadline. Payment is due on the contract's terms once the payee has sent a written request, the payer (other than the owner) has been paid for that work by the party above it, and the required lien waivers or sworn statements are in. Late amounts, other than retainage, which has its own release rule, then bear interest from the 14th day after payment was due, at the rate Florida sets for court judgments plus 12% a year, or the contract rate if that is higher.

That's one state. Check the law where the job is before you sign; a construction attorney can tell you which rules apply.

Keeping progress bills tied to real costs

A progress bill can look healthy on a job that's losing money, because billing follows the contract, not your costs.

For construction companies, expenses in Clyr carry the job and the cost code (a label for the type of work), so you can compare budget versus actual at billing time. On time-and-materials or cost-plus work, where the customer pays your costs plus a fee, any expense can be flagged billable, a percentage markup (what you add on top) is applied by your policy, and billable lines flow to your connected platform, such as your accounting or field service system, ready for invoicing.

FAQs

Is a deposit the same as progress billing?

No. A deposit is paid before work starts, while progress bills are earned by work done. Federal rules (FAR 32.102, March 2026 edition) make the same distinction: advance payments are "not measured by performance," unlike progress payments. If a job has both, say in the contract how the deposit gets credited against later progress bills.

Can a customer refuse to pay a progress bill?

A customer can dispute a bill, but state law may stop it holding back the whole thing over one problem. Florida's prompt payment law, for one, says a dispute doesn't let the payer withhold money for work the dispute doesn't affect, unless the contract says otherwise. Itemize each invoice so an argument over one line doesn't freeze the rest.

How often should you send progress bills?

Percentage-complete billing is usually monthly, on a cutoff date both sides know, and federal fixed-price construction contracts (FAR 52.232-5, May 2014 clause) call for monthly payments unless the contracting officer sets more frequent ones. A federal request must be proper to start the 14 days, and the government has 7 days to return a bad one. In Florida, a payer that finds an error must return the request within 14 days with written reasons, or interest runs anyway.

Do small service businesses use progress billing?

Yes, for any job big enough that waiting until the end would strain cash. A landscaping company installing a $40,000 commercial irrigation system, or an IT firm running a six-month network upgrade, can bill in stages like a general contractor. The difference is that usually no architect certifies the bill, so the contract has to say what counts as done.