What Is the Percentage of Completion Method?
The percentage of completion method is a way of recording revenue and profit on a long job as the work progresses, rather than when it ends. Most contractors measure progress by cost-to-cost: costs so far divided by total estimated costs, multiplied by the contract price, gives the revenue earned to date.
If you've spent $144,000 of an expected $480,000 on a $600,000 wiring job, the job is 30% complete and you've earned $180,000 of revenue, no matter how much you've invoiced so far.
Why contractors record revenue this way
Take a job that runs from October to June. Record everything when it finishes, and the first year shows costs with no income while the second shows a huge profit. Percentage of completion puts profit in the period the work happened, which is what lenders tend to want to see.
Billing and revenue answer different questions. Progress billing decides what you invoice and when, and it follows the contract. Percentage of completion decides what you've earned, and it follows the work.
The cost-to-cost formula
Repeat these each period:
- Percent complete = costs incurred to date / estimated total costs.
- Revenue earned to date = percent complete x contract price.
- Revenue this period = revenue earned to date - revenue recorded in earlier periods.
- Gross profit (revenue minus job costs) this period = revenue this period - costs this period.
The two numbers people forget to update are the estimate and the price. Estimated total costs means costs to date plus your current estimate of what's left, not the original bid. The contract price should include signed change orders, the approved changes to scope and price. And don't use the billing percentage as the percent complete: a schedule of values (the contract price split into pieces of work for billing) that puts too much of the price on early work creates fake profit.
Worked example: one job over two periods
A 12-person electrical contractor signs a $600,000 fixed-price contract to wire a medical office building, with $480,000 of estimated costs and a planned gross profit of $120,000, or 20%. Period 1 ends December 31, 2026. During period 2, which ends March 31, 2027, copper prices and a failed inspection push the estimate to $500,000.
| Period 1 | Period 2 | |
|---|---|---|
| Estimated total costs | $480,000 | $500,000 |
| Costs to date | $144,000 | $336,000 |
| Percent complete | 30.0% | 67.2% |
| Revenue earned to date | $180,000 | $403,200 |
| Revenue this period | $180,000 | $223,200 |
| Costs this period | $144,000 | $192,000 |
| Gross profit this period | $36,000 | $31,200 |
| Billed to date | $210,000 | $390,000 |
In period 1, $144,000 / $480,000 = 30%, and 30% x $600,000 = $180,000. That's the planned 20% margin (profit as a share of revenue).
In period 2, $336,000 / $500,000 = 67.2%, and 67.2% x $600,000 = $403,200. Subtract the $180,000 already recorded and revenue for the period is $223,200. After $192,000 of costs, gross profit is $31,200, a margin of about 14%.
That 14% is lower than the job's new overall margin of about 16.7% ($100,000 / $600,000) because period 2 also pays for period 1. Period 1 booked profit at 20% when the true figure turned out lower, and the correction lands in the period when you update the estimate.
Leave the estimate at $480,000 and the job looks 70% complete ($336,000 / $480,000), which records $420,000 of revenue, or $16,800 too much.
What the percent complete means for your billing
Contractors track this on a work-in-progress (WIP) schedule, a report with one row per open job. Compare earned revenue with what you've billed and you see whether a job is over- or underbilled.
At the end of period 1 the contractor has billed $210,000 but earned $180,000, so the job is $30,000 overbilled. That goes on the balance sheet, the report of what a business owns and owes, as a liability, because it's money billed for work not yet done. By the end of period 2, it has billed $390,000 and earned $403,200, so it's $13,200 underbilled. That's an asset: work done but not yet invoiced.
Overbilling helps cash, but it isn't profit, and the bill comes due in labor and materials later. Underbilling that grows month after month can mean slow invoicing, or an estimate that's too low, which inflates the percent complete.
Federal tax rules under section 460
Under Internal Revenue Code section 460, a contract to build, install or construct property that isn't completed in the tax year you entered into it is a long-term contract. Its taxable income generally has to be figured by percentage of completion, measured by comparing costs to date with estimated total costs. This is a federal rule, and states may not follow it.
There's an exemption for smaller contractors. A construction contract, meaning building, reconstruction, rehabilitation, improvement of real property or installing an integral part of it, such as wiring, is exempt if both of these are true:
- When you enter into the contract, you estimate it will be completed within 2 years of its commencement date. The regulations set that date as the day you first incur contract costs, such as design and engineering, other than bidding and negotiating.
- You meet the gross receipts test for the tax year you enter into the contract. For tax years beginning in 2026, Revenue Procedure 2025-32 sets it at average annual gross receipts of $32,000,000 or less over the 3 prior tax years.
Tax shelters can't use the exemption, and businesses under common control are generally counted as one. Each contract is tested in the year you sign it.
For contracts entered into in tax years beginning after July 4, 2025 (for a calendar-year business, contracts signed from January 1, 2026), the One Big Beautiful Bill Act exempts any residential construction contract, one where at least 80% of estimated costs go to dwelling units and related on-site improvements, whatever the contractor's size.
The cost capitalization rules in section 263A, which add indirect costs to the job's cost, still apply to a residential contract unless you meet the gross receipts test and expect to finish within 2 years, or 3 years for buildings with more than 4 units.
Exempt contractors can choose percentage of completion, a simplified exempt version of it, or the completed-contract method, among other permitted methods. Choosing a method for your first exempt contract needs no approval. Switching later is a formal change, usually made by filing Form 3115 under the IRS's automatic consent procedures, and it covers only contracts entered into from the first day of that tax year.
For contractors who aren't exempt, when a job finishes, the look-back method reruns the earlier years using actual costs, and you pay or receive interest on the difference on Form 8697. Contracts finished within 2 years with a price of no more than the lesser of $1,000,000 or 1% of your average gross receipts skip this. Your CPA can confirm how all of this applies to your entity.
Book accounting: revenue recognized over time
Your financial statements can follow different rules from your tax return. For statements under GAAP (generally accepted accounting principles, the US rulebook for financial reporting), the FASB revenue standard (Topic 606, as issued in 2014) says to record revenue over time when any of three things is true:
- The customer receives the benefit as you do the work.
- Your work creates or improves something the customer controls as you go, such as a building on its land.
- What you're making has no other use to you, and you have an enforceable right to be paid for work so far.
Most work on a customer's land fits the second one. The standard doesn't use the name percentage of completion, but cost-to-cost is one of the cost-based ways it allows for measuring progress, with limits. Costs that don't reflect progress stay out of the calculation, such as unexpected amounts of wasted material or labor. Materials bought for the job but not yet installed may need to earn revenue only at their cost, with no profit on top, under four specific conditions in the standard.
Keeping costs to date current
The percentage is only as good as the costs behind it, and field costs are the ones that show up late. A supplier bill sitting in a truck understates revenue this period and overstates it next. A tech swipes a card at the supply house, Clyr texts them, and once they reply with a photo of the receipt, the expense lands in your books coded to the right job. With job costing and a two-way sync with QuickBooks, Xero, Sage Intacct and NetSuite, that cost is on the job before you pull the numbers.
FAQs
Timing. Using the $600,000 job above, the completed-contract method shows no revenue or job costs in 2026, then the entire $600,000 and all of the costs in the year the job finishes. Total profit is identical. Completed contract can defer tax on an exempt contract, but GAAP statements can't simply use it when the work meets an over-time test. Many contractors use it on the tax return and report percentage of completion on the income statement, the profit report banks read.
Yes, once it's earned. Retainage is money the customer holds back from each payment until the job is finished. It's part of the contract price, so percent complete x price already includes it. The federal regulations say the same for tax: total contract price includes holdbacks and retainages.
Not fully. Section 56(a)(3) generally keeps percentage of completion for alternative minimum tax, a parallel federal tax calculation, even on contracts exempt from the regular rule. Residential contracts under the 2025 law are the exception. An ordinary C corporation isn't affected, so this mainly reaches owners of S corporations, partnerships and sole proprietorships, and the look-back method can follow it. Have a CPA run both calculations if you hold large exempt contracts.
On a tax return using this method, the formula shows the loss in stages. Say the $600,000 job's estimate rises to $650,000, with $390,000 spent. That's 60% complete, or $360,000 of revenue, so a $30,000 loss to date, with $20,000 still to come. GAAP statements can't wait: once a loss is evident, you book the whole expected $50,000, so the remaining $20,000 goes in this period. Tell your CPA as soon as the forecast turns.