What Are Pass-Through Costs?
Pass-through costs are expenses a business pays on a customer's behalf and then bills back to that customer, usually at the exact amount paid, instead of building them into its own price. Common examples are permit fees and equipment rentals in construction, and vendor repairs billed to owners or property taxes passed to tenants in property management.
When a roofing company in Ohio pays the city $350 for a permit to reroof a customer's house, the final invoice adds a separate line after the roofing price reading "Building permit, billed at cost: $350.00," with the city's receipt attached.
What makes a cost a pass-through
A cost is a pass-through when three things are true. It was spent for one customer or job, or it's a shared cost a contract lets you divide among customers, such as a building's property taxes. You can show exactly what it cost. And the customer agreed to pay it on top of your price.
That's the line between a pass-through and overhead. Office rent, truck payments and general liability insurance get built into your rates and prices. A permit for one address, a dumpster parked in one driveway or a plumber's bill for one rental unit belongs to one customer, so it can go on that customer's invoice.
Pass-through costs in construction
Typical construction pass-throughs are building permits and inspection fees, plan review fees, utility connection charges, dumpsters and disposal, equipment rentals, special testing, and charges from the building itself, such as an after-hours elevator operator on a commercial job.
How they're handled depends on the contract. On a fixed-price job, the contract says what the price includes, and items like permits or utility fees are sometimes carved out and billed back at actual cost. On a time and materials job, materials and rentals are billed as they're bought, often with a markup. On a cost-plus job, nearly all project costs are reimbursed at cost and the contractor earns a separate fee.
Pass-through costs in property management
Property managers pass costs in two directions. The first is toward owners. When a manager pays a plumber, a locksmith or a landscaper for an owner's property, the cost belongs to the owner, not the management company, and it appears on the owner statement, the monthly report of rent collected and bills paid for that property.
Say a property manager with 40 units replaces a water heater in one owner's rental for $1,180. If the management agreement allows a 10% coordination fee on repairs, the owner statement shows the $1,180.00 repair and a separate $118.00 fee. If it doesn't, the owner sees $1,180.00 and nothing else.
The second direction is toward tenants. Commercial leases often pass the building's property taxes and insurance through to tenants, and the shared costs of running common areas, like lobby cleaning and parking lot repairs, pass through as CAM charges, short for common area maintenance.
At cost or marked up
Billing at cost means the customer pays exactly what you paid. Billing with a markup adds a percentage on top, a handling charge for ordering the item, paying someone else's bill and carrying that money until the customer pays you back.
Either works if the contract says which applies, and to which costs, before the first invoice. A contractor might bill permits at cost and rentals at cost plus 10%. A customer who finds an undisclosed markup on a line labeled "at cost" has a fair complaint, and the next invoice gets read line by line.
Here is one month of pass-throughs for a general contractor finishing a tenant space in an office building. The second column applies 10% to every line to show the full effect:
| Pass-through line | At cost | At cost plus 10% |
|---|---|---|
| Building permit | $1,240.00 | $1,364.00 |
| Dumpster hauls (3 x $575.00) | $1,725.00 | $1,897.50 |
| After-hours elevator operator (building charge) | $360.00 | $396.00 |
| Total | $3,325.00 | $3,657.50 |
The markup adds $332.50 ($3,657.50 - $3,325.00), which is 10% of $3,325.00.
How pass-throughs show on the invoice and in the books
On the invoice, put pass-through costs on their own lines below your own work, with the vendor, the date and the amount, and attach the receipt. Label how each is billed: "at cost" or "cost plus 10%." A single line reading "misc. reimbursables: $3,325" is the kind customers dispute.
In the books, there are two common ways to record a pass-through, and both end with the same profit. Each entry below has a debit and a credit of the same amount, the two sides double-entry bookkeeping requires: a debit raises a cost or asset account, and a credit raises an income account or lowers cash or an asset. The example is the $1,725 of dumpster hauls, billed at cost:
| Step | Gross method | Net method |
|---|---|---|
| You pay the dumpster company | Debit job costs $1,725; credit cash $1,725 | Debit costs to rebill $1,725; credit cash $1,725 |
| You invoice the customer | Debit accounts receivable $1,725; credit reimbursed cost income $1,725 | Debit accounts receivable $1,725; credit costs to rebill $1,725 |
| Effect on the profit and loss statement (the report of income and costs) | $1,725 of income and $1,725 of cost | None |
Accounts receivable is the money customers owe you. "Costs to rebill" is a holding account on the balance sheet, the report of what the business owns and owes, and it empties when the invoice goes out. The gross method makes revenue look bigger without adding profit, which matters if you watch margin, your profit as a percentage of revenue. QuickBooks users will recognize the gross method as billable expense income, which applies when billable expenses are tracked as income.
If your books follow GAAP, the US accounting rules, the choice isn't yours to make freely. The test is who controls the item or service before it reaches the customer. If you do, you're the principal and record the full amount as revenue. If you only arrange for someone else to provide it, you're the agent and record just your fee or commission.
Signs of control include being the one responsible to the customer for the work, carrying the risk on it and setting the price. The Financial Accounting Standards Board (FASB), which writes those rules, explained the test in ASU 2016-08 in March 2016. Your CPA can confirm which side your pass-throughs fall on.
For a property manager paying a vendor out of the owner's money, the cost was never the manager's. It belongs on the owner's books and the owner statement, and the manager's own income is its fees.
Tax on reimbursed costs varies by state
Whether sales tax applies to a reimbursed cost depends on the state, and the rules don't line up.
In Washington, as of October 2026, WAC 458-20-111 covers the state's business and occupation (B&O) tax, a tax on a business's own gross income. It lets a business leave a reimbursement out of that income only when the customer alone is liable for the cost and the business pays it purely as the customer's agent, like an attorney paying court filing fees.
A contractor that owes the supplier for materials gets no exclusion, whether they were bought in its name or the customer's, and neither does a service or repair business for separately billed travel. Sales tax is a separate question: Washington's selling price definition allows no deduction for the seller's expenses.
In New York, sales tax regulation 526.5(e) says a vendor's expenses aren't deductible from its receipts, even when billed to the customer. A 2024 advisory opinion still quotes that rule and the court case behind it, where a trash hauler's landfill fees counted as part of its taxable charge.
A 2009 opinion, following a 2001 one on a computer services company, applied the idea to reimbursed travel: taxable when tied to taxable services or property, not when tied to nontaxable services. Advisory opinions apply only to the facts in them.
Other states draw these lines differently, and local taxes can add another layer. Check your state revenue department's guidance or ask your CPA before deciding how to tax a pass-through line.
Catching pass-through costs before they slip
Pass-throughs get lost because billing them depends on a receipt. The dumpster company gets paid on a company card, the receipt sits in someone's inbox, and the invoice goes out without the line. Clyr connects to the cards you already have. The moment one is swiped, the cardholder gets a text and replies with a photo of the receipt.
With billable expenses and markup, an expense, or one line of a split purchase, can be flagged billable with its own billing amount, and a percentage markup is applied automatically by your policy. Billable lines flow to the client side of your connected platform, or to owner statements in Buildium, with the documentation attached.
FAQs
They overlap, but the two terms point at different relationships. A pass-through cost is something you paid for a customer and bill to that customer. A reimbursable expense often means money an employee spent for the business and gets paid back for, such as mileage or a hotel. Contracts sometimes call pass-throughs "reimbursables," so go by the definition in the contract rather than the label.
Then you may not be able to bill them. On a fixed-price contract, the customer can fairly argue that your price covered everything needed to finish the job, permits and dumpsters included. Before signing, list the costs you plan to bill back, say whether each is at cost or marked up, and get the customer to sign off on that list.
Usually the customer, if the item is billed at actual cost. If the city raises permit fees or the landfill raises its disposal fee mid-job, the invoice shows the new amount. The exception is an allowance, a set budget amount for an item written into your price, where the contract decides who covers the difference.
Read the cap language. A not-to-exceed amount usually limits the total the customer will pay, so permits, rentals and other pass-throughs count against it unless the contract carves them out. If you expect a large outside fee, such as a utility connection charge, ask to exclude it from the cap by name or give it a separate cap.