Purchase Order vs Invoice: What's the Difference?
A purchase order (PO) is the document a buyer sends a vendor before a purchase to order goods or services at agreed prices, while an invoice is the bill the vendor sends after delivering them to ask for payment. The PO sets the terms of the deal, and the buyer checks the invoice against it before paying.
A landscaping company sends its supplier a $1,260 PO on Monday for 30 cubic yards of mulch at $42 a yard, and the supplier's $1,260 invoice, due in 30 days, follows the week after the mulch arrives on Thursday.
Purchase order vs invoice at a glance
| Purchase order | Invoice | |
|---|---|---|
| Who sends it | The buyer | The vendor |
| When | Before the goods or work | After delivery, or at agreed billing points |
| What it says | What to send, how many, at what price, where and by when | What was delivered, how much is owed and when it's due |
| Its number | A PO number, set by the buyer | An invoice number, set by the vendor |
| Legal role | An offer that becomes a contract once the vendor accepts | A request for payment under that deal |
| In the buyer's books | No entry | An expense or asset, plus a bill in accounts payable |
| Optional? | Yes, for most small purchases | No, it's how the vendor bills you |
The short way to keep them straight: the PO is your document, and the invoice is the vendor's. The invoice should quote your PO number so the two can be paired, while the vendor's invoice number is the one you record to avoid paying the same bill twice.
Where each one shows up in a purchase
The vendor may open with a quote. You answer with a PO. The vendor confirms, ships with a packing slip and then invoices. You pay, often with a remittance advice, a note telling the vendor which invoices the payment covers.
Real purchases don't always follow that line. Plenty of invoices have no PO behind them, like a $95 service call booked by phone. A subcontractor's PO often brings a monthly bill as the work progresses, each one billing part of the same order. And sometimes a bill comes before the goods, when a vendor wants a deposit on special-order materials.
How each one hits your books
A PO creates no journal entry, the dated record that moves an amount between accounts in your books. Nothing has been delivered and nothing is owed, so there's no expense and no debt to record. Open POs stay out of the general ledger, the master record of all your accounts.
The vendor's bill is different. On accrual books, which record costs when you incur them rather than when cash leaves, the mulch bill becomes an entry: debit Job materials $1,260 (the cost goes up) and credit accounts payable, the account for bills you owe vendors, $1,260 (what you owe goes up). When you pay, debit accounts payable $1,260 and credit Cash $1,260. Every entry has a debit side and a credit side that must be equal, and both of these do. On cash-basis books, nothing is recorded until you pay.
One wrinkle: on accrual books the cost belongs to the month the goods arrived, not the month the paper did. If the mulch arrives June 28 and the invoice on July 3, the June books should still carry the cost as an accrued expense, a cost you've incurred but haven't been billed for yet. Reverse it when you enter the July invoice so the cost isn't counted twice.
For taxes, the invoice matters too. IRS Publication 583 lists invoices among the documents that support business expenses, alongside canceled checks, account statements and credit card slips, and says those records should show the amount paid and that it was for a business expense. A PO shows neither. It records what you planned to buy.
Matching an invoice to its purchase order
Matching means putting the invoice next to the PO and checking that they agree before you pay. At a plain level, compare five things: the vendor, the PO number, the items, the quantities and the unit prices. Then look for anything the PO never mentioned, such as freight, a fuel surcharge or a shorter due date.
Take a property manager with 40 units who orders appliances for six unit turnovers, meaning units being readied for new tenants: six refrigerators at $849, six ranges at $629, and haul-away of the six old refrigerators at $25 each. The PO total is $9,018. The supplier bills $8,554:
| Line | Purchase order | Invoice | Difference |
|---|---|---|---|
| Refrigerators | 6 at $849 = $5,094 | 6 at $869 = $5,214 | $120 over the PO price |
| Ranges | 6 at $629 = $3,774 | 5 at $629 = $3,145 | 1 range not delivered or billed yet |
| Haul-away | 6 at $25 = $150 | 6 at $25 = $150 | None |
| Fuel surcharge | Not on the PO | $45 | $45 nobody agreed to |
| Total | $9,018 | $8,554 |
The bill is lower than the PO, and it's still wrong. The PO supports $8,389: $5,094 for the refrigerators at the agreed price, $3,145 for the five ranges delivered and $150 for haul-away. The other $165 ($120 + $45) needs an answer from the vendor, either a corrected invoice or a credit memo, a vendor document that reduces what you owe. The sixth range, $629, stays open on the PO until it arrives and is billed.
Set a tolerance so nobody chases pennies. A rule like "approve price differences under 1% or $25, whichever is smaller" would have caught the refrigerators, which came in about 2.4% over ($120 on $5,094).
Businesses that receive a lot of materials add a third document, the receiving record of what actually arrived, and check all three. That's three-way matching, and it catches a short delivery even when the invoice and the PO agree with each other.
When the PO and the invoice disagree on terms
Prices are the usual argument, and the answer is simple: the accepted PO's price is the deal, so a higher invoice price needs the vendor's explanation and your approval first.
Fine print is harder. The Uniform Commercial Code (UCC) isn't one national statute: it's a model code each state enacts in its own version, and Louisiana never enacted Article 2, its sales-of-goods part (Georgetown Law Library guide). Under UCC section 2-207, extra terms in a vendor's acceptance or written confirmation of a goods order, such as a late fee, are proposals to add to the contract.
Between merchants, which for this rule covers almost any two businesses, those terms become part of the deal unless your PO expressly limited acceptance to its own terms, the new terms materially change the deal, or you object, either in advance in your PO's terms or within a reasonable time after you see them. So a late fee printed on a vendor's confirmation can bind you if you say nothing.
Whether a later invoice counts as a confirmation, and what counts as material, depends on your state's version of the code, its courts and the facts. Services sit outside these goods rules. For a large order or a real dispute, a lawyer can tell you which terms hold.
Common mistakes with POs and invoices
Entering the PO as a bill
A PO keyed in as a bill records a debt for goods that haven't arrived and sets up a double payment when the real invoice shows up. Keep POs as purchasing records, and enter only the vendor's invoice in accounts payable.
Approving the total instead of the lines
An invoice total close to the PO can hide a price increase on one line and a short shipment on another, as the appliance order shows. Check line by line, every time.
Paying the PO amount
If the vendor billed for five ranges, pay for five. Paying the full PO total because "that's what we approved" sends money for goods you don't have and leaves you chasing a refund.
Matching invoices to POs in software
Matching gets skipped when it means a PDF in one window and a PO in another. Vendors email invoices straight into Clyr, line items are extracted automatically, and Clyr's bill pay and accounts payable tools add PO matching, flagging discrepancies in pricing or quantities. Approved bills are paid by ACH or check, and Clyr syncs two ways with QuickBooks, Xero, Sage Intacct and NetSuite.
FAQs
For the vendor, your PO is a sale waiting to happen. The vendor usually enters it as a sales order, its own internal record with its own number, and ships from that. Once the vendor delivers and bills you, the unpaid invoice sits in its accounts receivable, the money customers owe it, until your payment arrives.
Not on its own. A PO is a request to buy, and the vendor still has to bill you. Some buyer portals let a vendor turn your PO into an invoice with a click, copying the order lines. That saves typing, but the result is still the vendor's invoice, and it should show only what was delivered, not everything you ordered.
No. IRS Publication 583 says that, except in a few cases, the law doesn't require any specific kind of records, as long as your system clearly shows your income and expenses. POs are an internal control you choose to use. Invoices, receipts and bank records back up your deductions. Your CPA can tell you whether your lender or auditor expects more.
No. A pro forma invoice is a preview the vendor sends before delivery, showing what the final bill will look like, often so you can pay a deposit or prepare paperwork. It doesn't create a bill in your accounts payable. Record any deposit you pay as a prepayment, an asset on your books, and enter the real invoice when it arrives.
Yes. File it with the invoice and the proof of payment. Together they show the purchase was approved, what was agreed and what you paid, which is what an auditor, a lender or a customer on a cost-plus job, who pays your costs plus a fee, will ask to see. The invoice alone shows what the vendor billed, not what you agreed to pay.